ELECTRIC RATES
|
New rate will begin on
January 1st, 2012, – 1st bill
February 1st
Residential,
Farm, Public Authorities & Seasonal (RC 01, 03,
04, 07, 60, 62, 101, 104, 160)
Customer charge - $22.00 per month
First 600 kWh per month at .105 (600 kWh equals
$63.00)
Remaining kWh per month at .074
All
separately metered electric heat - .014 credit
per kWh
7 months (reading card October, first
bill in November)
A
service using over 75 KW will be billed under
the Large Power rate.
Heat credit
.014
Small Commercial
(RC40, 41, 43, 140)
Customer Charge -
$27.00
First 600 kWh
per month at .105 (600 kWh equals $63.00)
Remaining kWh per month at
.076
All
separately metered electric heat - .014 credit
per kWh
7 months (reading card October, first
bill in November)
A
service using over 75 KW will be billed under
the Large Power rate.
Heat credit
.014
Street Lighting
and Outdoor Lighting (RC70)(RC71 w/meter
services)
175
watt mercury vapor - $9.50 per month
Metered
400
watt mercury vapor - $14.50 per month
100-175 watt mercury vapor/metal
Lucalox
- $15.50 per month
halide high pressure sodium
$4.50
400W Metal Halide
- $15.50 per month
400 watt mercury vapor/metal halide $5.25
Irrigation (RC30)
Horsepower charge $20.00 per horsepower per
season
First 600 kWh of H.P per season at .076
Remaining kWh at .063
Small Power – 3
phase – 50 KW and under (RC 06, 50, 52)
Customer charge - $37.00 per month
(KW
– 25) x $9.00
First 100 kWh x KW x .10
Remaining kWh per month at .064
Separately metered electric heat - .014
per kWh
Large Power – 3
Phase – 50.01 KW and over (RC 80, 82, 83)
Customer charge - $37.00
(KW
– 10) x $9.00
First 100 kWh x KW x .078
Next 200 kWh x KW x .064
All
remaining kWh
x KW x .054
Separately metered electric heat - .014 per kWh
Metered Heat – RC
12, 13, 14, 15
Production
90
Miscellaneous
Rate Classes
Sub Meter
96 (electric heat)
Special
83
Dummy Acct.
99
|
FEES
Connection Fee $ 25.00
Deposit $200.00
Transfer Fee $ 15.00
Security Light Installation $ 75.00
Vandalized Security Light repair:
175 Watt $50.00
400 Watt $75.00
Bulb only $25.00
Meter Loop installation on existing pole $150.00
Staking Fee on new service (non-refundable) $150.00
Perfecting Fee on new service $150.00
Aid to construction on single phase overhead line build $2.50 per foot
Aid to construction on single phase underground line build $5.00 per foot
Aid to construction on three phase overhead line build $8.00 per foot
Aid to construction on three phase underground line build $13.00 per foot