Rate Schedule

Rates as of January 1st, 2019 - Current

Residential, Farm, Public Authorities & Seasonal
Facility Charge - $40.00 per month
First 800 kWh per month at .1125 (800 kWh equals $90.00)
Remaining kWh per month at .0825
All separately metered electric heat - Heat credit .02 (October - April)
A service using over 75 KW will be billed under the Large Power rate.  

Small Commercial
Facility Charge - $45.00
First 800 kWh per month at .1125 (800 kWh equals $90.00)
Remaining kWh per month at .0825
All separately metered electric heat - Heat credit .02 (October - April)
A service using over 75 KW will be billed under the Large Power rate.  

Street Lighting and Outdoor Lighting

175 watt mercury vapor $11.00 per month 
400 watt mercury vapor $17.00 per month 
Lucalox  $18.00 per month
150/175 Metal Halide $11.00 per month
400W Metal Halide $18.00 per month   
LED 70 W $11.00 per month
LED 100 W $17.00 per month

Metered Security Lights

100-175 watt mercury vapor/metal halide high pressure sodium $5.00 
400 watt mercury vapor/metal halide  $6.00 

Irrigation Controlled Rate
Horsepower charge $25.00 per horsepower per season
$3.50 per KW per month
All KWH at $0.0565

Irrigation Non-Controlled Rate
Horsepower charge $25.00 per horsepower per season
$13.50 per KW per month
All KWH at $.0675

Irrigation Pivot Only
Service Minimum $480.00 per season ($40 per month)
All kWh at .0925

Small Power – 3 phase – 50 KW and under     
Facility Charge - $60.00 per month
(KW – 25) x $13.50
(First 100 kWh x KW) x .1125
Remaining kWh per month at .0825
Separately metered electric heat - Heat credit .02 per kWh(October - April)

Large Power – 3 Phase – 50.01 KW and over  
Facility Charge - $80.00
(KW – 10) x $13.50
(300 kWh x KW) x .0675
Remaining kWh per month at .0575
Separately metered electric heat - Heat Credit .02 per kWh (October - April)                       

                                                 
FEES

Late Charge  

$12.50
1.5% interest of unpaid
balance into billing

Connection Fee     

$25.00  

Deposit  

$200.00

Transfer Fee

$15.00

Security Light Installation      

$75.00

Vandalized Security Light repair:  

175 Watt
400 Watt
Bulb only                                   

$50.00
$75.00
$25.00

Meter Loop Fee       

$150.00

Staking Fee on new service (non-refundable) 

$150.00

Perfecting Fee on new service   

$150.00

Aid to construction on single phase overhead line build

$5.00 per foot

Aid to construction on single phase underground line build  

$5.00 per foot

Aid to construction on three phase overhead line build 

$13.00 per foot

Aid to construction on three phase underground line build

$13.00 per foot